A study on the cost factors of prefabricated buildings under the Engineering Procurement Construction model based on the interpreted structural model

Author(s)

Mei Qing

Corresponding Author:
Mei Qing
Affiliation(s)

Management College, Sichuan University of Science & Engneering, Sichuan 643000, China

Abstract

In order to promote the transformation of China's construction industry to industrialization and promote the sustainable development of the construction industry. Based on the interpreted structure model, the influence factors of prefabricated building cost are considered in the EPC project general contracting model, and the cost influencing factor structure model of design stage, procurement stage and construction stage is constructed. Under this model, the various factors are interrelated to form a complex system, and the relevant data are from the ISM group composed of relevant experts in the construction industry. Results indicate that the rate of prefabricated, component usage, the output of a file, and inventory management is surface factor affecting the cost, the usage of machinery and equipment, the geographical location of a file, the level of the hoisting installation, field management level and the causes of the rationality of the component split is an intermediary, standar disation of the modulus, the degree of professional design personnel and the special requirements of project owner is the root cause. In order to further reduce the cost of prefabricated buildings, it is necessary to strengthen the skill training of designers and standardize the uniform modulus standards.

Keywords

prefabricated building, interpretation of structural models, EPC engineering general contracting, cost

Cite This Paper

Mei Qing. A study on the cost factors of prefabricated buildings under the Engineering Procurement Construction model based on the interpreted structural model. Academic Journal of Business & Management (2020) Vol. 2, Issue 1: 86-99. https://doi.org/10.25236/AJBM.2020.020110.

References

[1] Li Dezhi, Li Xin. Research on driving factors of prefabricated buildings based on interpretative structural model [J]. Building economy,2019,40(01):87-91.(in Chinese)
[2] Zhao Liang, Han Quqiang. An evaluation study on influencing factors of prefabricated construction cost [J]. Construction economy, 2008,39(05):25-29. (in Chinese)
[3] Kang Xiaohui, Sun Jinying, Jin Zhanyong, et al. Analysis of influencing factors on development efficiency of prefabricated buildings [J]. Building economy,2019,40(03):19-22. (in Chinese)
[4] Shen Jinshan, Hua Yuanpu, Yuan Ming. Research on lean cost management of prefabricated building [J]. Construction economics,2019,40(03):45-49. (in Chinese)
[5] Chang C.G., Zhang Y. (2017) Optimization Model Under Grouping Batch for Prefabricated Components Production Cost. In: Xhafa F., Patnaik S., Zomaya A. (eds) Advances in Intelligent Systems and Interactive Applications. IISA 2017. Advances in Intelligent Systems and Computing, vol 686. Springer, Cham.
[6] Zhang S., Pan Y., Li N., Sun Q. (2011) A Comparative Study of the Direct Costs Between Prefabricated Housing System and the Traditional Construction Technology—A Case Study of Precast Concrete Wall Panel. In: Yang D., Qian Y. (eds) Proceedings of the 18th International Symposium on Advancement of Construction Management and Real Estate. Springer, Berlin, Heidelberg.
[7] Jerjeas G. Top 10 Areas for Construction Productivity Improvement on Albert Oil and Gas Construction Projects[C]. Construction Research Congress 2010: Innovation for Reshaping Construction Practice -Proceedings of the 2010 Construction Research Congress, Banff, AB, Canada: Construction Institute of ASCE, 2010:1030-1038.
[8] Li Y, Pei Z. The Application Value of BIM Technology in Prefabricated Building Based on EPC General Contracting Management Model[J]. Leadership and Management in Engineering, 2011.
[9] Back W E, Moreau K A. Cost and schedule impacts of information management on EPC process [J]. Journal of management in engineering, 2000, 16(2): 59-70.
[10] Haron N A, Hassim S, Kadir M R A, et al. Building cost comparison between conventional and formwork system: A case study on four-story school buildings in Malaysia[J]. American Journal of Applied Sciences, 2005, 2(4): 819-823.
[11] Feng T, Tai S, Sun C, et al. Study on cooperative mechanism of prefabricated producers based on evolutionary game theory[J]. Mathematical Problems in Engineering, 2017.