Welcome to Francis Academic Press

Academic Journal of Engineering and Technology Science, 2021, 4(5); doi: 10.25236/AJETS.2021.040508.

Study on Estimation Method of Ground Settlement around Pile Foundation Caused by Dewatering

Author(s)

Xia Wu

Corresponding Author:
Xia Wu
Affiliation(s)

School of Architecture Engineering, Jiangxi College of Applied Technology, Ganzhou, 341000, China

Abstract

According to the character that the seepage amount of pile foundation is large during the construction period in karst water-rich area, and take the fact that the drops of water level lead the settlement of the ground around the pile foundation into account, a method of surface settlement estimation based on diving full well and steady seepage was analyzed. According to the seepage theory, the effective stress increment of soil unit around the pile foundation was deduced. By means of the double integral within the scope of two-dimension range, the settlement due to seepage effect and its estimation formula of surface around the pile foundation was analyzed. On the basis of real project of NO.3 section of Hechi-Du’an Expressway in Guangxi Zhuang Autonomous Region, the ground settlement was forecasted through the way of field measurement and formula estimation respectively. Facts and figures show that the measured value is consistent with the estimation value, but within the scope of 3m apart from the pile edge, the measured value is greater than the estimation value. The result can provide certain reference for the forecast of ground settlement created by dewatering.

Keywords

Pile foundation, Ground settlement, Seepage, Estimation method, Karst area

Cite This Paper

Xia Wu. Study on Estimation Method of Ground Settlement around Pile Foundation Caused by Dewatering. Academic Journal of Engineering and Technology Science (2021) Vol. 4, Issue 5: 44-47. https://doi.org/10.25236/AJETS.2021.040508.

References

[1] Zhensheng Li. Durability Analysis of Concrete Pile Foundation of Super Tall Building Under Dry-wetting Cycle [J]. Journal of Lanzhou Institute of Technology,2021,28(04):19-23.

[2] Wei Guo, Wang Cai, and Yuxiao Ren. Numerical Analysis of the Influence of Pipe Jacking Construction on Pile Foundation of Viaduct [J]. Science Technology and Engineering, 2021,21(22): 9598-9604.

[3] Chao Hu. Settlement calculation and influencing factor analysis of pile foundation in Xiangfu viaduct [J]. JOURNAL OF TRANSPORT SCIENCE AND ENGINEERING,2020,36(02):98-103.

[4] Guangzhong Lin. Numerical analysis of settlement calculation of bridge pile foundation in karst area [J]. Journal of Fujian University of Technology, 2018,16(01):13-16.

[5] Shiru Wen. Estimation Method for Ground Settlements of the Karst Tunnel in Soil Surrounding Rock [J]. MODERN TUNNELLING TECHNOLOGY, 2018,55(06):73-79.

[6] Chaoqun Wei, Qinglu Deng. Research on application of distributed optical fiber monitoring technology for subgrade settlement[J]. Journal of Engineering Geology,2020, 28(5): 1091-1098.

[7] Guisheng Wang, Xing Chang, and Futao Han. Three-dimensional slope stability analysis based on strength theory of unsaturated soil [J]. South-to-North Water Transfers and Water Science & Technology, 2017,15(01):199-203.

[8] Hui Dong, Xiao Luo. FIELD TESTS ON SEEPAGE REGULATION OF AGGREGATE GRAVEL SOIL UNDER ARTIFICIAL HEAVY RAINFALL [J]. Journal of Engineering Geology , 2015, 23(04):616-623.

[9] Shiru Wen, Xiaohua Yang, and Yuanshu Guo. Interpretation based on frequency spectrum energy analysis of ground penetrating radar detection image [J].Advanced Engineering Sciences, 2020, 52(6):120-130.

[10] Jishu Sun, Bochao Qiu, and Tian Xiao. Analysis on water damage mechanism and influencing factors of embankment slope under rainfall [J]. Journal of Hebei University of Science and Technology, 2021,42(04):415-423.